Fail Over Deployment

Hi Support,

I have work with partner on new deployment for Peplink Balance 380X x 2units. We need to deploy as fail over method.

During testing, when we testing fail over from master Balance 380X to Slav Balance 380X, it lost connection 7-8 ping before, so please kindly check and advise on this case. we don’t need it to lost connection because Banking customer is important on connection fail over.